Metering Skid FAT: The Factory Acceptance Test Checklist That Protects Your Schedule

  • This topic is empty.
Viewing 1 post (of 1 total)
  • Author
    Posts
  • #13849
    admin
    Keymaster

      FAT is the last moment a problem costs you days instead of months. After a metering skid leaves the factory, every defect compounds: site access, crane bookings, commissioning windows and — for custody transfer — the ticket you cannot legally print until accuracy is proven. A disciplined metering skid FAT factory acceptance test procedure for buyers prevents all of that in two days of witnessing. This checklist comes from the manufacturer's side of the table: these are the tests a serious integrator expects you to demand, and the witness points during metering skid factory testing that deserve your personal presence rather than a report attachment.

      custody transfer metering skid under fabrication and quality inspection before FAT

      The FAT checklist items that matter for a fiscal metering skid

      Ten line items separate a real fiscal FAT from a photo opportunity. Insist that every FAT checklist items for fiscal metering skid below appears in the approved test plan — with acceptance criteria and pass/fail records — before fabrication finishes:

      ✅ 1. Hydrostatic / pressure test. Whole assembled pipework at design pressure, witnessed, with a signed test record and certificate.

      ✅ 2. Instrument calibration certificates. Every flow meter, transmitter, thermometer and densitometer traceable to a recognized metrology institute — check serial numbers against the delivered hardware, not a template.

      ✅ 3. Wet or dry calibration verification of the complete measurement run. Not the datasheet — the assembled run, under FAT conditions, with uncertainty stated.

      ✅ 4. Loop-by-loop I/O and function test. Every transmitter-to-PLC-to-HMI loop exercised and signed; alarm and interlock logic proven, including 2oo3 shut-off votes on loading service.

      ✅ 5. Flow computer configuration review. Compensation equations, meter factors, ticket format and audit trail verified against the approved data sheet.

      ✅ 6. Software version and cybersecurity check. Exact software build recorded; user levels, record retention and backup/restore demonstrated live.

      ✅ 7. Emergency shutdown and purge sequence test (especially for gas or special-gas service), with positive-pressure cabinet alarm chain proven.

      ✅ 8. Hazardous-area documentation audit. Ex certificates for every certified device — KEYPOINT positive-pressure cabinets, for example, carry Ex db eb ib mb pxb IIC T6 Gb with TSG supervision-inspection certification — plus a labeling and earthing continuity check.

      ✅ 9. Dimensional, coating and nameplate inspection against approved GA drawings, including lifting arrangements and preservation for shipping.

      ✅ 10. Punch-list discipline. A FAT without a documented punch list, closure deadline and re-test rule is not an acceptance — it is a ceremony.

      These FAT checklist items for fiscal metering skid projects are the difference between acceptance and ceremony: insist on all ten, in writing, before the build plan is frozen.

      Witness points: what you must see in person

      Travel for three tests; accept reports for the rest. From experience, the witness points during metering skid factory testing that repay the flight are the pressure test, the calibration verification of the complete measurement run, and a live shut-off/safety sequence demonstration. Everything else can be witnessed by report or video. During the calibration witness, ask one question: "show me the measurement run uncertainty, and where it is traceable to." A confident answer arrives with certificates and instruments; a hesitant one arrives with adjectives. In-person witnessing is also the anchor of any credible metering skid FAT factory acceptance test procedure for buyers — reports can be attached, but presence is what keeps the test honest. At KEYPOINT, customer witnesses are scheduled into the build plan from order confirmation — pressure test, loop test and wet calibration are staged so your inspector sees each under power, not as a post-hoc video.

      metering skid workshop fabrication and quality certificates during factory acceptance

      The paperwork to collect before the skid ships

      Leave the factory with the complete dossier, or you will chase it for the life of the asset. Before signing the FAT certificate, collect: signed hydrotest record; all instrument calibration certificates; loop check sheets; software version record and backup media; Ex certificates and TSG documentation; as-built P&IDs, wiring diagrams and GA drawings; and the FAT report including the closed punch list. This dossier is exactly what an auditor, a customs surveyor or the counterparty's metrologist will ask for later — and manufacturing it afterwards is far harder than signing it on the day. For the documentation package a qualified supplier should provide across the whole project, see our guide on choosing a custody transfer metering skid manufacturer.

      ✅ Bottom line: A fiscal-grade FAT is ten checklist items, three in-person witnesses and one complete dossier. Demand all three and the skid that arrives on site starts printing defensible tickets in week one.

      FAQ

      Q: How long should a metering skid FAT take?

      A: Plan two to three days on site for a single-run skid: one for pressure and dimensional checks, one for loop and software demonstration, one reserved for calibration verification and punch-list closure. Multi-run or special-gas skids add a day.

      Q: Can FAT be done remotely if travel is not possible?

      A: Partially. Video witnessing covers loop tests and documentation review well, but pressure testing and calibration verification deserve in-person presence or an appointed third-party inspector — these two records carry the most weight in later custody-transfer audits.

      Q: Does KEYPOINT include FAT in the standard delivery scope?

      A: Yes. Every custody-transfer metering skid from Shanghai KeyPoint Controls Co., Ltd. ships with witnessed pressure test, loop test and calibration verification as standard scope, with customer witnesses scheduled from order confirmation — an ISO 9001-certified process backed by our full certificate package.

      Next Step

      Ask us for the full metering skid FAT factory acceptance test procedure for buyers template — the KEYPOINT engineering team will share the checklist, acceptance criteria and witness-point schedule we execute on every skid, so your next FAT protects your schedule instead of testing it. Contact Shanghai KeyPoint Controls Co., Ltd. at zhuzm@keypoint.cn.